gstommylee
Registered User
- Jan 31, 2012
- 14,507
- 2,801
Agreed
What would have pushed back a possible december announcement was a serious FEIS appeal that takes it into next year. That appeal never came.
Agreed
Is the construction schedule such that they can start anytime in the year? Obviously not until NHL signs off on something. But, for example, if NHL gives a franchise in March, can construction start immediately then?
I know that starting more or less immediately is necessary for a 2020-21 start, but I'm thinking about an easier timeline for construction if it's a 2021-22 start.
Well, the construction schedule I think is flexible. As you probably have seen here, the thinking of the Leiweke's is that they would like to get started within 30-60 days. Frankly, it's entirely possible that they go back to New York next week, make their presentation, get the Executive Committee to vote to recommend the bid to the full BoG, get the city to waive that specific clause which you are referring to here (and since Durkan will be back there, she could easily grant that waiver then and there if she wanted to) and you'd see dirt moving down there perhaps within a week or two after that meeting. That's why this waiver clause is so important. It keeps from there having to be a specific response in order for something to occur, instead, all it may need is for the actual recommendation to occur before something happens. Flexibility my friend, flexibility.
Granted, you're probably not going to hear anything publicly from the league after next week's meeting - even though CD5 and the rest of the Seattle media band will be back there waiting outside the meeting ready to pounce on Bettman and Daly - but the real clues will come in more succinctly, like whether you see construction equipment/cranes/workers start to move in to begin demolition on the site. That crane strike that we were talking about here from earlier this month has now ended so they have all available resources to work with if they want to get started. It's all going to be more about what you see on the ground here in Seattle than what you hear from back in NY because yes, they won't announce anything publicly until December's full meeting. But if all that I outline above occurs, you could be well into demolition before that vote. Really, your best bet will be to perhaps pay attention here and over on the threads at Sonics Rising because the info on the ground here will be more telling than anything you hear out of Bettman or Daly's mouth at this point.
Thanks.
Suppose the ExComm delays. No positive word until December. No waiver until Jan of 2019. What I know of the construction schedule means that leaves a 2020 start all but impossible. So, the team and league would await 2021. In that case, could demo start in Jan 2019? I assume so. Would it be cheaper because there would be 8 more months to work with?
The requirement was no construction starts before December until there is a guarantee of a team. There is no need to delay construction like that.
Thanks.
Suppose the ExComm delays. No positive word until December. No waiver until Jan of 2019. What I know of the construction schedule means that leaves a 2020 start all but impossible. So, the team and league would await 2021. In that case, could demo start in Jan 2019? I assume so. Would it be cheaper because there would be 8 more months to work with?
I don't think that question has been legitimately answered/asked of those involved specifically OVG. One would naturally assume so. The one thing to consider is that, correct me if I am wrong, there is nothing scheduled there after October 5th and I believe would either one begin construction asap or start scheduling again under your scenario. Anything I have read has not suggested construction delay or postponement /reschedule of events there. Construction beginning asap seems to be all they are thinking about.
In either scenario finishing asap seems to be OVG's priority to start scheduling events again.
Thanks.
Suppose the ExComm delays. No positive word until December. No waiver until Jan of 2019. What I know of the construction schedule means that leaves a 2020 start all but impossible. So, the team and league would await 2021. In that case, could demo start in Jan 2019? I assume so. Would it be cheaper because there would be 8 more months to work with?
The requirement was no construction starts before December until there is a guarantee of a team. There is no need to delay construction like that.
So are we still on schedule for 2019-2020? My OCD can't handle the current conference imbalance for much longer...
(Grips for the thought of NHL pulling an MLS/Cincinnati and announcing for a team in 2019 with 10 months lead time. Only to maximize the comedy.)
(Also, names the team Kraken just to see the resulting meltdown.)
NOTE: None of the parenthetical advice being offered here is either advisable or practical. Nor is this an actual endorsement of Kraken.
(Grips for the thought of NHL pulling an MLS/Cincinnati and announcing for a team in 2019 with 10 months lead time. Only to maximize the comedy.)
(Also, names the team Kraken just to see the resulting meltdown.)
NOTE: None of the parenthetical advice being offered here is either advisable or practical. Nor is this an actual endorsement of Kraken.
(Grips for the thought of NHL pulling an MLS/Cincinnati and announcing for a team in 2019 with 10 months lead time. Only to maximize the comedy.)
(Also, names the team Kraken just to see the resulting meltdown.)
NOTE: None of the parenthetical advice being offered here is either advisable or practical. Nor is this an actual endorsement of Kraken.
I'm not 100% sure how big of a meltdown Kraken would be..
Life is beautiful when the only issue is ''What will the team be named ?''
Aren’t Kranken mythical sea creatures who live in the North Atlantic? What does that have to do with Seattle?
The leading contender...seems to be...The Metropolitans...